The project
- Target: 1.6 GW of AI factory capacity through 2028.
- Built: about 42 MW inside CDC facilities in Melbourne.
- Original first phase: 150 MW with 18,500 GB300 GPUs.
- Outcome: the Project Southgate partnership ended by mutual agreement in 2026.
The site story
Firmus is now building its own sites. In Tasmania it targets about 288 MW at Long Reach, Bell Bay, on a cleared industrial platform with three 220 kV lines already running through it.
That is a brownfield site choice. The land and the high-voltage lines are already there, which is often the fastest path to a working AI factory.
Lessons for operators and investors
- Announced capacity is not delivered capacity.
- Partners need to agree on sites as well as capital.
- A brownfield site with existing high voltage can move faster than greenfield land.
- Investors should test the site pipeline behind the headline number.
How Divine Lab Worx would approach it
We test every site in a pipeline on the same basis and separate announced capacity from approved and buildable capacity. Project Southgate shows why that separation matters to lenders. See investor due diligence.
Planning a project like this? Divine Lab Worx finds sites that can actually be built, anywhere in Australia. Book a discovery call or call 0468 017 373.
Sources and further reading
- Baxtel, Firmus and CDC scrap 1.6GW Project Southgate with 42MW built (6 October 2026)
- DCD, Firmus targets 288MW data campus in Tasmania (June 2026)
- NVIDIA Newsroom, NVIDIA expands AI infrastructure capacity with Australia’s data centre ecosystem (9 September 2026)
This case study analyses publicly reported information as at October 2026. Divine Lab Worx was not involved in this project. Figures are as reported by the sources listed. Not financial, legal or engineering advice. Divine Lab Worx is the consultancy arm of Sharktech Global.