The question used to be where the land is. Now it is where the power is, and when you can connect.

The grid is the new bottleneck

AEMO now forecasts data centres as a stand-alone demand category. It has flagged that by 2030 a single fault near western Sydney could cut about 1,500 MW of data centre load within milliseconds. In March 2026 the Australian Energy Market Commission proposed new rules for large data centre loads, including requirements to ride through some grid disturbances. The message to developers is consistent: involve grid planners before you lock in a site, a lease or a construction schedule.

What power ready actually means

  1. Headroom: spare capacity at the supplying zone substation, net of other committed loads.
  2. Timing: a realistic connection or upgrade date from the network operator’s planning reports.
  3. Resilience: standby generation, UPS and the ability to ride through disturbances.
  4. Fit: supply that suits the deployment, from a 100 kW edge node to a multi-megawatt hub.

Indicative sizing

As an indicative planning figure, five to eight 25 kW compute units need about 135 to 240 kVA, assuming 80 per cent average IT load with cooling included. A 1.3 MW hub needs about 1.8 to 1.9 MVA and typically a new high-voltage connection and its own substation. Peak demand, power factor and redundancy are confirmed by a load study before any connection request.

Avoiding phantom capacity

Connection queues hold many speculative requests. A site that looks available on paper may sit behind several projects that never proceed. That is why we pair the desktop screen with an electrical load study and an early connection enquiry on the preferred site. See power-ready site screening.

Need a location anywhere in Australia? Tell us your load and region. We will find existing infrastructure that fits. Book a discovery call or call 0468 017 373.

Dainu Devis

Chief Executive Officer, Sharktech Global

Dainu Devis is the Chief Executive Officer of Sharktech Global, the Australian technology group and parent company of Divine Lab Worx. He sets the group's vision: put artificial intelligence to work across Australian industry, on Australian infrastructure, delivered end to end by one accountable team. Under his leadership, Divine Lab Worx finds data centre ready sites anywhere in Australia, deploys and maintains GPU infrastructure with its own managed delivery crew, and advises businesses in every industry on adopting AI. Sharktech Global also builds products for critical infrastructure, hospitality and industrial safety. Dainu holds a Master of Engineering Science from UNSW and advises operators, developers, boards and governments on where to build, what to secure and how to turn strategy into revenue. More about Divine Lab Worx and Sharktech Global.

Sources and further reading

This article is general commentary for infrastructure operators, developers and investors. It is not legal, planning or engineering advice. Figures are indicative planning figures. Divine Lab Worx coordinates qualified Australian specialists within each engagement. Divine Lab Worx is the consultancy arm of Sharktech Global.