Data centre development applications are reaching council desks that have never assessed one. The building looks like a warehouse, but the questions are different: how much power it will draw, how it will be cooled, what its backup generators will sound like at 2am, and whether the promised jobs will exist once construction ends. This guide sets out what a council assessment team should check, and what to ask the applicant for when the information is missing.
Key points:
- Power, cooling, noise and fuel storage drive most of the risk in a data centre application, not the building itself.
- Ask for evidence, not intent: a network connection response, a cooling design with water use figures, and a noise assessment that includes generator testing.
- Operational jobs are usually far fewer than construction jobs, so test the community benefit claims.
- Larger proposals may be assessed by the state rather than council. Check the state significance thresholds that apply in your state early.
What should a council check first in a data centre development application?
Start with the assessment pathway and the power. Confirm whether the proposal sits with council or with the state planning authority, because larger data centres can cross state significance thresholds. Then ask whether the electricity network can actually supply the site. A data centre that cannot get a grid connection on the timeline it claims will either stall or fall back on on-site generation, which changes the noise, air quality and fuel storage picture.
How do you test the power claims?
Ask for the applicant's correspondence with the network service provider: at minimum a connection enquiry response stating the capacity available and the expected connection date. Large new loads now face stricter connection rules, covered in our explainer on the 30 megawatt grid connection rule. Check that the stated capacity in megawatts matches the building size and the cooling design, and ask what happens if the connection is delayed.
What should you ask about water and cooling?
Cooling is where water use is decided. Evaporative cooling can use large volumes of water in hot weather, while air-cooled and closed-loop liquid systems use far less but more electricity. Ask the applicant to state the cooling method, peak and annual water demand, the water source, and what happens during drought restrictions. Compare the figures with the local water utility's capacity rather than accepting a single annual average.
How should noise be assessed?
Data centres run around the clock. The main sources are rooftop chillers and fans, plus backup diesel generators, which are tested regularly even when the grid never fails. Ask for a noise assessment that covers night-time operation at the nearest homes, names the generator testing schedule, and models the full number of generators running at once. Conditions on testing hours and maximum generator run time are common and reasonable.
What about fuel, batteries and fire safety?
Backup generators mean diesel storage on site, and uninterruptible power supply systems often use large lithium-ion battery rooms. Ask for the fuel storage volumes and bunding, the battery chemistry and capacity, and the fire engineering approach, and confirm the local fire authority has been consulted. Check whether on-site generation will need an environment protection licence in your state.
Do fibre, traffic and the site itself matter?
Fibre rarely raises planning objections, but diverse fibre routes into the site usually mean new trenching in public roads, so ask where the routes will run. Construction traffic is heavy; operational traffic is light. Treat the site like any industrial proposal for flooding, bushfire, contamination, heritage and visual bulk, and check the decommissioning plan for when the equipment reaches end of life. Our seven variables for a data centre site covers the site tests developers use.
How do you test the community benefit claims?
Ask the applicant to separate construction jobs from ongoing operational roles, and to state how many operational roles will be local. Ask what the facility will contribute beyond rates: local procurement, training, use of waste heat, or network upgrades that benefit other users. A credible applicant can answer each of these in writing.
What information should the applicant provide?
| Topic | Ask for |
|---|---|
| Power | Network service provider response, capacity in megawatts, connection date, fallback plan |
| Cooling and water | Cooling method, peak and annual water demand, water source, drought plan |
| Noise | Night-time assessment at nearest homes, generator testing schedule, all generators running case |
| Fuel and batteries | Diesel volumes and bunding, battery chemistry and capacity, fire engineering, fire authority consultation |
| Fibre and traffic | Fibre route plans, construction traffic management plan |
| Community benefit | Construction and operational roles, local share, contributions beyond rates |
Who can help a council review a data centre application?
Divine Lab Worx offers a Council Data Centre Application Review: an independent technical review of a lodged application against the checks above, with a written list of gaps and the questions to put to the applicant. It is a fixed fee, quoted up front, and does not replace the council's own planning assessment or legal advice. Divine Lab Worx is the data centre and critical infrastructure consultancy arm of Sharktech Global, led by Chief Executive Officer Dainu Devis, a former critical infrastructure manager. Where a project needs implementation, such as managed IT, cyber security or AI consulting and agent security, Sharktech Global delivers it.
Sources and further reading
- NSW Planning Portal
- Planning Victoria, Department of Transport and Planning
- Divine Lab Worx, the 30 megawatt grid connection rule explained
- Divine Lab Worx, regional NSW data centre sites after the 2026 inquiry
This article is general information for Australian councils and local government officers. It is not planning or legal advice. Divine Lab Worx is the consultancy arm of Sharktech Global, led by Chief Executive Officer Dainu Devis.