On 5 November 2026 the New South Wales Legislative Council's Public Accountability and Works Committee tabled its report on data centres. It makes 26 recommendations to the NSW Government. Three months earlier, on 5 August, the state introduced a bill giving the energy minister new powers over who connects large loads to the grid. Together they change the questions a developer has to answer before committing to a site, and they change them most for sites outside Sydney.

This article is for developers, operators and investors weighing land in the Hunter, the Central West and Orana, or New England. It sets out what was decided, what is still a recommendation, and what to check now.

What the inquiry recommended

The committee received 143 submissions and held five public hearings. It did not recommend a pause on approvals: members voted six to one to remove draft moratorium wording. Instead it asked for a state data centre and AI strategy, assessment of cumulative impacts across existing, approved and proposed facilities, and designated precincts steered towards areas with energy, water and land capacity, away from homes.

The headline energy recommendation is that data centres source all of their energy from renewables matched hour by hour, not offset across a year. The report also recommends incentives for demand flexibility, less reliance on diesel backup, mandatory public reporting on energy, water and emissions, a community benefit framework, and a user-pays approach to utility infrastructure.

26 Recommendations to the NSW Government in the Legislative Council data centre inquiry report tabled on 5 November 2026.

Water is where the Sydney story and the regional story diverge. Sydney's data centres mainly draw drinking water, and Sydney Water projections cited in the inquiry suggest the sector could reach up to a quarter of Sydney's drinking water demand by 2035. The committee wants recycled water, rainfall-independent cooling and full-cost pricing. A regional site with a credible non-potable water source, or a cooling design that needs little water, now answers a question every approval body will ask.

The grid access powers are already law in waiting

The inquiry is advice. The Electricity Infrastructure Investment Amendment Bill 2026 is not. It lets the energy minister declare a large load infrastructure access scheme over all or part of the state, and that scheme can authorise or prohibit access to specified network infrastructure. It applies to any facility with a network connection able to carry 5 megawatts or more. Data centres must pay for the network they need, and other customers must not carry that cost.

This is the same model New South Wales used to ration access in its renewable energy zones. For a developer it means connection is no longer only a negotiation with a network business. It may also depend on whether your site sits inside a declared scheme, and on what that scheme charges.

What it means for the Hunter, the Central West and New England

Each of these regions sits on or near a renewable energy zone: Hunter-Central Coast around Newcastle, Central-West Orana around Dubbo, and New England around Tamworth and Armidale. That proximity to new generation is the obvious attraction if hourly matching becomes a condition. It is not a guarantee of access. Transmission into those zones is being built for generators first, and a large load scheme could set its own rules and fees on top.

The precinct recommendation cuts both ways. A region named as a precinct would gain a clearer path. A site outside one could face harder questions on cumulative impact. Until the government responds, treat precinct status as unknown, not assumed.

Proximity to new generation is an attraction, not a guarantee of access.

Seven questions to answer before you commit

  1. Which network asset would serve the site, and could it fall inside a declared large load access scheme?
  2. What would hourly-matched renewable supply cost from generation in the nearest zone, including firming?
  3. Where does cooling water come from, and does the design work without drinking water?
  4. What is already approved or proposed nearby, so you can answer a cumulative impact assessment?
  5. What would a community benefit offer look like for this town, before anyone asks?
  6. Can the facility report energy, water and emissions publicly from day one?
  7. Does the project qualify for the state's assessment pathway, and is the application ready for it?

The national picture adds to this. The Australian Energy Market Commission's advice, released on 5 August 2026, proposes that large data centres match consumption with new renewable certificates, contract firming, register as market participants and support demand flexibility. National Cabinet agreed on 26 August 2026 to develop national data centre standards, with Commonwealth legislation expected in early 2027. A regional New South Wales project will likely answer to both layers.

Who can help

Divine Lab Worx is the consultancy arm of Sharktech Global, led by Chief Executive Officer Dainu Devis. We work through site, power, water and approval questions with developers before capital is committed, and coordinate qualified specialists where engineering, planning or legal advice is needed. For the strategy work itself, see Sharktech Global's business consultancy service. Once a site is running, Sharktech's team that manages critical infrastructure maintenance supports operators, with most work delivered remotely and site visits quoted.

Key takeaways

  • The inquiry report tabled on 5 November 2026 makes 26 recommendations and does not call for a moratorium.
  • It recommends hourly-matched renewable energy, recycled water, cumulative impact assessment and designated precincts.
  • The Electricity Infrastructure Investment Amendment Bill 2026 gives the energy minister control over grid access for loads of 5 megawatts or more, with data centres paying for the network they need.
  • Sites in the Hunter, the Central West and Orana, and New England sit near renewable energy zones, but access is not guaranteed.

Dainu Devis

Chief Executive Officer, Sharktech Global

Dainu Devis is the Chief Executive Officer of Sharktech Global, the Australian technology group and parent company of Divine Lab Worx. He sets the group's vision: put artificial intelligence to work across Australian industry, on Australian infrastructure, delivered end to end by one accountable team. Under his leadership, Divine Lab Worx finds data centre ready sites anywhere in Australia, deploys and maintains GPU infrastructure with its own managed delivery crew, and advises businesses in every industry on adopting AI. Sharktech Global also builds products for critical infrastructure, hospitality and industrial safety. Dainu holds a Master of Engineering Science from UNSW and advises operators, developers, boards and governments on where to build, what to secure and how to turn strategy into revenue. More about Divine Lab Worx and Sharktech Global.

Sources and further reading

This article is general commentary for infrastructure developers, operators and investors. It is not legal, planning or engineering advice. Divine Lab Worx coordinates qualified Australian specialists within each engagement.