The money
- A$35 billion+ of data centre financing raised by operators in 2026, a record.
- A$24 billion raised in all of 2025.
- 85% of 2026 funding is debt.
- Seven times the 2020 to 2024 annual average.
- Operators named: AirTrunk, CDC, Firmus, Goodman, Macquarie Technology, Stack and Equinix.
Six case studies
- The Anthropic data centre at Western Downs: power drove a regional site.
- IREN Bundey, 800 MW: an existing grid connection wins.
- Project Southgate: 1.6 GW announced, 42 MW built.
- NVIDIA AI factories: modular units need ready sites.
- OpenAI NEXTDC at Eastern Creek: corridor sites carry grid risk.
- The next national supercomputer: plan the site before the system.
The pattern
There is plenty of data centre financing and the hardware is ready. The projects that move first have power, land and approvals lined up.
The Reserve Bank is watching for a bubble, which makes independent site evidence even more important for lenders. Good data centre site selection is now part of the credit case.
Where the data centre investment opportunities are
- Regional sites near generation and transmission.
- Existing grid connections and brownfield industrial land.
- Prepared sites for modular AI factories.
- Guideline-ready sites in NSW and Victoria.
- Next-generation research and sovereign supercomputing.
Each of these data centre investment opportunities depends on the site being proven first. See the investment picture.
Planning a project like this? Divine Lab Worx finds sites that can actually be built, anywhere in Australia. Book a discovery call or call 0468 017 373.
Sources and further reading
- ABC News, Data centre funding surges to record $35b this year (23 September 2026)
- NVIDIA Newsroom, NVIDIA expands AI infrastructure capacity with Australia’s data centre ecosystem (9 September 2026)
- Commercial Real Estate, Anthropic anchors proposed $32bn Queensland data centre (18 September 2026)
- W.Media, IREN targets Bundey transmission hub for 800MW campus (June 2026)
- Baxtel, Firmus and CDC scrap 1.6GW Project Southgate with 42MW built (6 October 2026)
- W.Media, OpenAI and NextDC unveil AUD 7bn plan for sovereign AI campus in Sydney (December 2025)
- Information Age (ACS), Australia’s top supercomputer may see closure if not replaced (13 October 2026)
This case study analyses publicly reported information as at October 2026. Divine Lab Worx was not involved in this project. Figures are as reported by the sources listed. Not financial, legal or engineering advice. Divine Lab Worx is the consultancy arm of Sharktech Global.